Another export contract for the supply of cranes for hydroelectric power plants in Uzbekistan

Another export contract for the supply of cranes for hydroelectric power plants in Uzbekistan

As part of the program for the development of hydroelectric stations in Uzbekistan, the construction of the largest Pskem hydroelectric power station on the river. Pskem – the upper step of the Chirchik cascade.

Our company will directly participate in this project by supplying the first two bridge cranes with a capacity of 63+5t and 63/12t for the installation and maintenance of mechanical equipment in the chamber of the main and emergency gates of the construction and operation tunnel of the station.

The contract for the supply and provision of services for supervised installation of cranes was signed in January this year. And already in August the cranes will be successfully delivered to the station.

Recall that this is not the first project to supply HPPs in the Republic of Uzbekistan with our cranes.